The short version
Every dam on the list, one square each
DHPD is the source. "Under implementation" is DHPD's own label for projects that are not listed as under construction. A megawatt (MW) measures how much electricity a dam can make.
Dams flood land and need roads, tunnels and workers' camps. To use forest land for that, a company has to ask the government for permission. This is called a forest clearance. The requests are filed on a website called Parivesh.
Forest area is counted in hectares (ha). A football pitch is about 0.7 ha, so the pitch comparison is only a rough guide. Each project is counted once, even if it applied more than once.
Where all the requests stand
"Fully approved" means the government has given final permission. It does not mean the trees have been cut. This data does not say how much forest has actually been cleared on the ground.
A few dams account for most of the forest
The ten biggest requests make up almost all of the forest area. The colour shows what happened to each one.
The ten biggest forest requests
A river basin is the land that drains into one river system. Grouping the requests by basin shows where the pressure is.
Forest requested, by river basin
Basins are as listed on DHPD. Three projects that are on Parivesh but not on DHPD have no basin on DHPD, so they sit under "Not on the DHPD list".
Both websites are official, so you would expect them to match. We lined up the two lists, dam by dam. Each square below is one dam from the DHPD list, coloured by what Parivesh says about its forest request.
Does each dam have a forest record?
We do not say which website is right. A difference only shows that the two do not match.
What this page can and cannot tell you
- Approved is not the same as cleared on the ground. The data says permission was given. It does not say how many trees were cut.
- Parivesh is missing recent requests. Our Parivesh file only covers requests filed before 28 June 2022. A dam with no record may simply have applied later.
- We matched the lists by dam name. Names are spelled differently on the two sites, so a few matches were made by hand. They are listed on the last tab.
- The numbers are a floor, not the full picture. They cover only what the two websites show.
Want the detail? Use the tabs at the top: forest requests, the dams, where the sites disagree, how we did this.
Forest requests in detail
What the four decisions mean
By river basin
By district
Basins and districts are the DHPD values for each matched project. Yammeng and Halaipani are placed where DHPD places them, even though Parivesh gives a different district (see the "Where the two sites disagree" tab). Attunli, Etalin and Anonpani are shown in Dibang Valley, the district the project owner gives, although DHPD says Lower Dibang Valley (also listed on that tab).
Every project with a forest request
Area is each project counted once. The extra proposals for refilings are explained on the "How we did this" tab.
The dams on the list
Power capacity by river basin
All dams on the DHPD list
Developer All
† DHPD does not give a basin for these dams. The basin was worked out from the district by a rule.
Where the two sites disagree
Every difference we found, sorted into groups. We do not say which site is right. The project owner's own notes are quoted where they exist.
Dams found on only one website
On DHPD, but not on Parivesh
Developer All
† Basin worked out from the district, not given by DHPD. Missing from one website does not tell us which website is incomplete.